On Tuesday, March 21, Vogts-Parga Construction of Newton re-opened Winn Road to traffic just south of Northwood Lane.
Due to recent deterioration of a culvert, Winn Road over the culvert has
been closed for more than a year while City of Salina staff prepared the
documents for a replacement project and Vogts-Parga completed the
construction.
In addition to the culvert replacement, the project included removal and
replacement of the pavement over the culvert, excavation and
embankment around the culvert, and the replacement of a water line under
the culvert.
Despite weather and other typical construction delays, the project
proceeded largely as planned and met the original anticipated completion
date of mid-March.
The $193,000 project was part of the City of Salina's $4.7 million 2022
street maintenance capital improvement program.