News Releases

10/18/2019 - Mill & Inlay Work Continues

On Saturday through Wednesday, October 19 through 23, APAC Shears of Salina will continue work on the City of Salina's annual asphalt mill and inlay project. The schedule is as follows, weather permitting:

Paving:

SA

SU

M

TU

W

 

19

20

21

22

23

Ash, Broadway to Ninth

SA

SU

M

TU

W

Ash, 3rd to Ohio

SA

SU

M

TU

W

The work consists of milling the existing asphalt street surface 1.5" and replacing it with new asphalt to rehabilitate and preserve the pavement section. Permanent pavement markings will be placed shortly after the resurfacing.

The roads will likely be closed during construction. Motorists are encouraged to seek alternate routes to their destinations.

The $1.5 million project is a major component of the City of Salina's $4.7 million 2019 maintenance capital improvement program.