News Releases

7/20/2022 - Mill and Inlay Work Continues Further

 

On Thursday and Friday, July 21st and 22nd, APAC Shears of Salina will continue working on the City of Salina’s annual asphalt mill and inlay project.  The schedule is as follows, weather permitting:

 

Milling

M

T

W

TH

F

18

19

20

21

22

Oakdale Avenue, Oakdale Drive to Iron

M

T

W

TH

F

 

Paving

M

T

W

TH

F

18

19

20

21

22

Pacific, Santa Fe to Front

M

T

W

TH

F

Pacific, 1000’ east of Front east to the city limits

M

T

W

TH

F

 

Pavement Repair

M

T

W

TH

F

18

19

20

21

22

Cloud, Broadway to Ohio

M

T

W

TH

F

 

The work consists of milling the existing asphalt street surface 1.5” and replacing it with new asphalt to rehabilitate and preserve the pavement section.  Permanent pavement markings will be placed shortly after the resurfacing.

 

Oakdale and Pacific will be closed to through traffic while the work is completed.  Two way traffic will be maintained during the work on Cloud.  Motorists should expect modest delays and are encouraged to avoid the work zones altogether if possible.

 

The $916,000 project is a major component of the City of Salina's $4.7 million 2022 maintenance capital improvement program.